Plan Management allows the user to manage
the plans used in their projects. A single plan can be used for multiple
projects. When changes are made to the plan, they will automatically flow
to the associated projects with the exception of option
status.
Plans will be maintained in the data library
only. Making changes (add and remove) to the activities and options on
a plan will be done in the data library. Option status can be made available,
lot dependent, pricing, standard or unavailable and the option may be
made price-overrideable. These settings are set in the data library, but
can be overridden at the project level and if the plan is used in multiple
projects, it can have different overrides in the different projects.
Tasks
|
Steps
|
Add Plan
Back to Top
|
Navigation Path
Data Library > Plans
Steps
- Select the Add
Plan Template link.
- Use the text field to enter the Plan # and required
Plan Name.
- As desired, use the text field to enter the Plan
Description, Square Footage, # of Bed Rooms # of Bath rooms, default Retail
Price, and the default schedule template.
Note: Default Retail Price can be used to populate a price when you
associate with a new project. When you associate this plan to a new project
the default price will be populated as the sales price. We recommend
- Click the Save
Button.
|
Edit Plan
Back to Top
|
Navigation Path
Data Library >Plans > Edit
Steps
- Select the Edit
link from the Actions column.
- All of the fields are editable. When
any change is made, it will update this plan across the application.
- Select the Save
button to save the changes.
Note: The user can set
the default schedule for each plan in two areas;
- DL > Plans > Edit -
The default schedule set in the DL will only be used to set the default
schedule for the next project the plan is used in.
- Admin > View > Manage Plans > Edit - The
default schedule set here can override the schedule set at the DL.
|
Manage Plan Activities
Back to Top
|
Navigation Path
Data Library > Plans > Activities
Note: Deleting an activity from an option will remove
the activity code from the option on all plans, bids, and contracts in
which the option activity appears
Steps To Add Plan Activities
- Select the Add
Activity Code link.
- Select the Activity(ies) to be added to the plan
by entering the qty for unit-of-measure activities, or check the box for
turnkey activities.
- Select the Add
Selected Activities button to add the activity(ies) to just this
plan or select the Add Selected &
Add To Additional Plans to add the activity(ies) to additional
plans.
Steps To Delete Plan Activities
- Select the checkbox(es) next to the appropriate
activity.
- Select the Delete
Selected to delete the activity(ies) from just this plan or select
the Delete
Selected & Delete From Additional Plans to delete the activity(ies)
from additional plans.
Steps To Edit Plan Activities
- Select the Edit
link for the activity.
- Use the text field to modify the Template Budget
and Scope of Work.
- Select Update Options
- Update Contracts, Flag Changes - Automatically
updates contracts and flags the activity that changed
- Update Contracts, Don't Flag Changes - Automatically
updates contracts and does not flag the changed activity
- Only Flag Changes - Flags the changed activity
only
- Select the Save
button to update the activity or Save
& Update Additional Plans button to save and select other plans
to update.
- Select the plans to update
- Select the Update
Selected Plans button.
Steps To Archive a Plan Activity
- Select the Edit
link.
- Select the Status equal to "Inactive"
- Select the Save
button to update the activity or Save
& Update Additional Plans button to save and select other plans
to update.
- Select the plans to update
- Select the Update
Selected Plans button.
Steps To Add Activity Package
- Select the Add
Activity Package link.
- Select the Activity package(s) to be added to
the plan.
- Select the Add
Selected button to add the activity(ies) or Add
Selected & Add to Additional Plans button to save and select
other plans to update.
- Select the plans to update
- Select the Add
to Selected Plans button.
Steps To Edit Plan Activity Package
- Select the Edit
link for the activity.
- Use the text field to modify the Template Budget
and Scope of Work.
- Select the Save
button to update the activity package or Save
& Update Additional Plans button to save and select other plans
to update.
- Select the plans to update
- Select the Update
Selected Plans button.
Steps To Archive a Plan Activity Package
- Select the Edit
link for the activity.
- Select the Status equal to "Inactive"
- Select the Save
button to update the activity or Save
& Update Additional Plans button to save and select other plans
to update.
- Select the plans to update
- Select the Update
Selected Plans button.
|
Manage Plan Options
Back to Top
|
Navigation Path
Data Library >Plans > Options
Steps To Add Options
- Select the Add
Option Code link.
- Select the option(s) to be added to the plan.
Select how you want Bidding and Contracting to be notified of the change;
- Update Contracts,
Flag Changes - This will update all contracts that have this option
code or activity code and will flag the contract that there are changes
to the activity code(s) and/or option code(s) associated to the contract
- Update Contracts,
Don't Flag Changes - This will update all contracts that have this
option code or activity code and will not flag the contract that there
are changes to the activity code(s) and/or option code(s) associated to
the contract.
- Only Flag
Changes - This will flag the contract that there are changes to
be applied to the activity code(s) and/or option code(s) associated to
the contract.
- Select the Add
Selected button to add the option(s) or Add
Selected & Add to Additional Plans button to save and select
other plans to update.
- Select the plans to update
- Select the Add
to Selected Plans button.
Steps To Edit Plan Option(s)
- Select the Edit
link for the option.
- Select the radio button to make the Pricing,
which is the option retail price fixed or overrideable.
- Use the text box to add or edit the Option
Description.
- Select the drop-down box to change the Option
Status
- Available - The option is an available selection
on the plan
- Lot Dependent - The availability of the option
on the plan is dependent on the lot selected.
- Pricing - Available to cost the option, but
not available for sale
- Standard - The option is a standard selection
on the plan
- Unavailable - The option is not available
on the plan.
- Use the text box to add or edit the Internal
Notes.
- Modify the Activity(ies) attached to the option.
- Select the Edit
Activities link at the top of the screen.
- Use the text box to enter the new quantity
for unit of measure activities.
- Select Update
Options
- Use the text box to enter or edit the Scope of Work.
- Use the radio button to make the activity
Status inactive.
- Enter template budget amounts as applicable.
- Select the Save
button to update the activity(ies) or Save
& Update Additional Plans button to save and select other plans
to update.
- Select the plans to update
- Select the Update
Selected Plans button.
- Select the Save
button to update the option or Save &
Continue button to save and select other plans to update with the
new Option Status.
NOTE: Changes to Name, Description, Internal Notes, and/or Pricing AUTOMATICALLY
updates this option in all associated plan(s). Option status does not
automatically flow from changes made at the Data Library Plan Option tab,
however you can flow down to the project with the Update Additional Plans
button.
- Select the plan(s) to update with the current
plan option status. Select one of the following to continue;
- Select the Update
Selected button to update the option status on this plan and not
update the status anywhere else.
- Select Exit
to discard changes and exit this screen.
- Select the plan(s) to update with the current
plan option status. The plans displayed are plans at the data library.
Select Update Selected & Continue or Skip
to update option status at the project level.
- Select the
plans to update at the project level with the current plan option status.
The plans displayed are plans within projects.
- Select the Update
Selected button to update the option status on this plan and remain
on this
screen.
- Select Update
Selected & Exit to
update option status at the project level and continue to the Option List
Screen.
- Select Exit
to discard changes and exit this screen.
|
Manage Projects
Back to Top
|
Navigation Path
Data Library >Plans > Projects
Steps To Associate a Plan to a Project
- Select the Associate
Project link.
- Select the Project(s) to add the plan too.
- Select the Associate
Selected Projects button to associate the plan to the project(s).
Steps To Archive Plan from Project
- Select the Edit
link for the project.
- Select the Status equal to "Archived"
- Select the Save
button to update the plan.
Steps To Remove Plan from Project
- Select the Remove
link for the project.
NOTE: If
the plan is associated to one or more lots, it can not be removed from
the project. Either
remove the plan from all lots or change the Plan Project status to "Archived".
Associate Plans to Lots
- Select the Lots
link
- Select the Associate
Lots link.
- Select the lot(s) to add the plan too.
- Select the Associate
Selected Lots button to associate the plan to the lot(s).
Archive a Plan from Lot
- Select the Lots
link
- Select the Edit
link.
- Select the Status equal to "Archived"
- Select the Save
button to update the plan.
Remove a Plan from Lot
- Select the Lots
link
- Select the Remove
link.
NOTE: If there are
any workups on the lot that include the plan, the plan can not be removed
from the lot. The
Plan Lot status can only be made "Archived".
|
Copy Plan
|
Navigation Path
Data Library >Plans > Copy
Steps
- Select the Copy
link from the Actions column.
- System will prompt you to click OK
to continue copying a plan.
- A copied plan will appear below the original plan.
|
Delete Plan
Back to Top
|
Navigation Path
Data Library >Plans > Delete
Steps
- Select the Delete
link from the Actions column.
- System will prompt you to click OK
to continue deleting a plan.
Note: If the
plan is associated with any projects, the plan cannot be deleted. The
plan should be 'Archived' instead.
|