Map Activities to Schedule Tasks
Back to Top
|
Via Schedules Tab
Navigation Path
Data Library > Schedules > Task-Activity Relationship
Notes
Draw activity packages cannot be linked to schedule tasks; all other
activity packages can be linked to a task as a single activity can.
Steps
- Select the Task-Activity
Relationship link.
- Select either
Activity tab or Activity Packages
tab.
- Select ---None---
(or other
task) link under Task column
to drop down a list of all tasks in the schedule template.
Select the schedule template task to map the Activity or Activity Package
to that task.
- Click the Save
button to save changes.
Via Activities Tab
Navigation Path
Data Library > Activities > Activities or Activities tab >
Tasks
Steps
- Select the Tasks
link for the activity you wish to map to a schedule. All active schedule
templates will be displayed, with the task currently mapped to this activity
in the drop down box.
- Drop down the activity list and select the task
you wish to assign to the activity or activity package.
- Select the Update
or Update & Exit button to save changes, or the Cancel
button to exit this screen.
|
Update From Activity List
Back to Top
|
Navigation Path
Data Library > Schedules > Task-Activity Relationship > Update
from Activity List
Notes
This process will update the schedule template based on the activities/activity
packages mapped to scheduled tasks in the lot-specific activity list selected.
(Since it updates an existing schedule template, the template must be
in use in at least one lot.)
Steps
- Select Update
from Activity List link.
- Select the Project
- Select the Lot
- Select the Save
button to update the Task-Activity Relationships in the schedule template.
|