Future Price Change

Revised October 24, 2008

Description

Future Price Changes take place when the trade partner tells you that there is going to a price change in the future and they have the new pricing available.

 

 

Tasks

Steps

Create Revision

 

 

 

Back to Top

Navigation Path

BC  > Contracts > TK > View > Create Revision

 

Note: Creating a revision copies the current contracts pricing so that you can edit the newly created contract and the contract that was copied can remain open.

Steps

  1. Select Create Revision.
  2. Another contract for the same trade partner is created in the Contract tab with the status of 'Contract'.

 