BTHelp for BTSales | © BuildTopia 2008 |
---|
Revised May 8, 2009
Each task not completed today should be updated to reflect a new projected start or finish date. Schedule updates are communicated in real time to communicate changes effectively to all users in the system, particularly trade partners who are reviewing the schedule with an eye to commencement or completion dates planned for their contracted tasks.
The user with Project Management permissions can update scheduled tasks by modifying the task projected start or finish date for one task and then by bumping other tasks in the selected lot schedule. This section describes the processes and steps to update work which is not completed.
Primary Task |
Associated Task |
|
|
|
Tasks |
Steps |
Update Task Projected Dates
|
Navigation PathPM > Lot Matrix > Review Schedule > Edit PM > Lot Matrix > Project Quick Schedule > Edit PM > Lot Matrix > Project Day Schedule > Select Task Name PM > Lot Matrix > Project Week Schedule > Select Task Name Notes
Steps
|
Bump Schedule
|
PM > Lot Matrix > Review Schedule > Edit > Update Task PM > Lot Matrix > Project Quick Schedule > Edit> Update Task PM > Lot Matrix > Project Day Schedule > Task > Update Task PM > Lot Matrix > Project Week Schedule > Task > Update Task
|
Contact Customer Support: 1-800-411-2020 Option 4 or support@buildtopia.com |
---|