You are here: Data Library > Schedules > Manage Task-Activity Relationship
 Help for BTBuilder © BuildTopia 2009

Manage Task-Activity Relationship

Revised May 5, 2009

Description

Schedule tasks may be linked to activities for PO generation. This relationship drives PO generation and approval per the lot schedule update - work approval process.

 

Notes

NOTE: Task-Activity mapping does NOT copy when importing a schedule template from a lot.

 

Primary Task

Map Activities to Schedule Tasks

Update from Activity List

 

 

Tasks

Steps

Map Activities to Schedule Tasks

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Back to Top

 

Via Schedules Tab

Navigation Path

Data Library > Schedules > Task-Activity Relationship

Notes

Draw activity packages cannot be linked to schedule tasks; all other activity packages can be linked to a task as a single activity can.

Steps

  1. Select the Task-Activity Relationship link.
  2. Select either Activity tab or Activity Packages tab.
  3. Select ---None--- (or other task) link under Task column to drop down a list of all tasks in the schedule template. Select the schedule template task to map the Activity or Activity Package to that task.
  4. Click the Save button to save changes.

Via Activities Tab

Navigation Path

Data Library > Activities > Activities or Activities tab > Tasks

Steps

  1. Select the Tasks link for the activity you wish to map to a schedule. All active schedule templates will be displayed, with the task currently mapped to this activity in the drop down box.
  2. Drop down the activity list and select the task you wish to assign to the activity or activity package.
  3. Select the Update or Update & Exit button to save changes, or the Cancel button to exit this screen.

Update From Activity List

 

 

 

 

 

 

 

Back to Top

Navigation Path

Data Library > Schedules > Task-Activity Relationship > Update from Activity List

 

Notes

This process will update the schedule template based on the activities/activity packages mapped to scheduled tasks in the lot-specific activity list selected. (Since it updates an existing schedule template, the template must be in use in at least one lot.)

Steps

  1. Select Update from Activity List link.
  2. Select the Project
  3. Select the Lot
  4. Select the Save button to update the Task-Activity Relationships in the schedule template.

 

 

Contact Customer Support: 1-800-411-2020 Option 4 or support@buildtopia.com